Wednesday, 29 March 2017

March Progress

Works continue apace in the ground at Malvern Vale with the vast majority of the major bulk shift of cartaway now being completed. The site is stoned up, foundations going in and will soon be ready for the superstructure to commence.

Externally the perimeter walls have commence adjacent the footpath areas - these will ultimately provided the secure boundary of the site. 






Please note that Ian Hodgkiss is no longer involved with the Malvern Vale Primary School Project. 

Paul Morris has taken over the Site Management of the project with immediate effect and will work alongside Rob Portman.

Pauls contact details are –

Tuesday, 14 March 2017

Out of Hours Working


On Thursday March 23rd we at SpellerMetcalfe will pouring and finishing the concrete slab at the New Primary School. The operation needs to be done in one hit to get the correct finish on the concrete. However as it is also weather dependent it may be that the operation continues beyond our normal working hours into the evening/night. We will do our best to minimise any noise and apologies for any inconvenience in advance