Our works on the Primary School are currently winding down, little heavy traffic shall be arriving on site and disruption should be minimal. The last few finish touches are being added so here are few photos.
This blog is designed to give an update on the Malvern Vale Primary School Project as works progress through 2017.
Friday, 8 June 2018
Monday, 21 May 2018
May Update
It has been some time since the last post, a lot of things have happened. The fixed furniture in most of the rooms is now in place. The outside has been tarmacked and there it is not likely that any other heavy plant will be arriving. Its should start to get quieter on site.
This is the reception room that is almost finished.
This is the reception room that is almost finished.
And in my opinion the best feature of this room is the microwave.
Monday, 9 April 2018
April Update 1
Week 3 of the hall photos, note that the floor is completed. Check the Malvern Vale Facebook page out for the full 360 photo.
Saturday, 24 March 2018
Wednesday, 14 March 2018
March Update 2
Wednesday, 7 March 2018
March Update 1
Now that the snow has gone, work can continue at the school. We recently acquired a 360 camera so we can now do wide angle photos and eventually 360 photos. The picture below is of Class 5, the fixed furniture has now been installed on the left. The teaching wall is on the right.
This is a picture of the hall below, currently it is in less of a complete than the class rooms.
Monday, 26 February 2018
February Update 2
Within the last few weeks there have been some editions to the site. The soffit boards have just started going up as well as additions inside, such as the plumbing, hand dryers and doors in the toilets.
Wednesday, 14 February 2018
February Update 1
Over the last month the school is having the fixed furniture installed. Also the brick work on the outside is almost complete with just some pointing to go.
Tuesday, 30 January 2018
January Update 4
Just a heads up, there will be a road sweeper going round this Friday.
The water and gas is also likely to be installed in the near future so there maybe some disruption on the roads.
The water and gas is also likely to be installed in the near future so there maybe some disruption on the roads.
Monday, 15 January 2018
January Update 3
It seems to be getting warmer and lighter but winter is still here, inside the school thing are warming up. The ceiling and lights are going in at one end of the school and the toilet floors are also going down. Here's some pictures to show the recent progress.
Monday, 8 January 2018
January Update 2
Over the past few weeks the ceiling tiles and frames have started to go into place. This means the lighting can be installed showing the school in its finished lighting. The picture on the left is of the newly installed internal doors and on the right is the lit toilets.
Tuesday, 2 January 2018
January Update
As 2018 begins, the second fix continues. All the scaffolding has gone so there will be no shots from the roof anymore. The skirting boards as well as the latex for the flooring is being added to the junior area of the school and the sprinkler house is almost finished. The two pictures featured are the reception area and the cloak room for year 6.