Just a heads up, there will be a road sweeper going round this Friday.
The water and gas is also likely to be installed in the near future so there maybe some disruption on the roads.
This blog is designed to give an update on the Malvern Vale Primary School Project as works progress through 2017.
Tuesday, 30 January 2018
Monday, 15 January 2018
January Update 3
It seems to be getting warmer and lighter but winter is still here, inside the school thing are warming up. The ceiling and lights are going in at one end of the school and the toilet floors are also going down. Here's some pictures to show the recent progress.
Monday, 8 January 2018
January Update 2
Over the past few weeks the ceiling tiles and frames have started to go into place. This means the lighting can be installed showing the school in its finished lighting. The picture on the left is of the newly installed internal doors and on the right is the lit toilets.
Tuesday, 2 January 2018
January Update
As 2018 begins, the second fix continues. All the scaffolding has gone so there will be no shots from the roof anymore. The skirting boards as well as the latex for the flooring is being added to the junior area of the school and the sprinkler house is almost finished. The two pictures featured are the reception area and the cloak room for year 6.
Subscribe to:
Posts (Atom)