Wednesday, 13 September 2017

August 17

The school summer holidays and have been and gone - and works continue apace on site at Malvern Vale. Since the last update the timber frame erection has continued with a crane towering over the site. As that process nears a close we move towards the internal 1st fix installations as well as the external finishes to the building.

Over the next month the following activities will continue/commence

  • The scaffold continues to be struck and the single ply roofing is complete on parts of the building.
  • The M&E and Sprinkler works will continue
  • 1st Fix Carpentry
  • Velfac Windows are going in
  • Externally the Corium cladding is being fixed to outside of the building
  • Blown fibre insulation is being pumped into the walls.
  • Plastering Works







As we move inside the building the numbers of trades persons on site will increase but the overall number of large deliveries will decrease. 

If you any issues please do not hesitate to contact the site team.







No comments:

Post a Comment