Over the next month the following activities will continue/commence
- The scaffold continues to be struck and the single ply roofing is complete on parts of the building.
- The M&E and Sprinkler works will continue
- 1st Fix Carpentry
- Velfac Windows are going in
- Externally the Corium cladding is being fixed to outside of the building
- Blown fibre insulation is being pumped into the walls.
- Plastering Works
As we move inside the building the numbers of trades persons on site will increase but the overall number of large deliveries will decrease.